Hanoi Party chief calls for speedy completion of 2nd metro line
The Hanoi Party Committee Secretary has called for speeding up work on the elevated section of the Nhon-Hanoi Railway Station to complete it by next year.
Inspecting the city’s second metro project Monday, Dinh Tien Dung said the entire 12.5-kilometer line from Nhon in the western district of Nam Tu Liem to the downtown Hanoi Railway Station must be operational by 2025.
It comprises 8.5 kilometers of elevated tracks with the rest being underground.
« This is not just to satisfy the wish of Hanoi but to protect the prestige of the contractor, » he said.
The city Party chief ordered that the construction of the elevated tracks must be completed before Oct. 15 next year so that the section could start operation within next year.
He directed related units to focus on solving difficulties and problems to boost the overall progress of the project.
For now, Hyundai E&C-Ghella, the main contractor, has put the four-kilometer underground section on hold, citing failure to hand over the land needed for it. It complained in July that it does not have the land to build S11, one of the four underground stations.
The city’s compensation policy for affected households has yet to be approved.
City leaders have organized various meetings to discuss the problem and find solutions.
Nguyen Cao Minh, director of the Hanoi Metropolitan Railway Management Board, said 74 percent of the work has been finished, including 89.5 percent of the elevated section and 33 percent of the underground section.
During his inspection tour, Dung called on authorities to work together to find a solution within this month.
Work on the Nhon-Hanoi Railway Station line began in 2010 at an estimated cost of $1.2 billion and was scheduled to be completed in 2017. But there have been several delays, which have also pushed the cost to $1.55 billion.
Most of the funding for the project comes from official development assistance loans.
By Vo Hai – VnExpress.net – November 30, 2021
Articles similaires / Related posts:
- Hanoi metro tickets to cost $0.35-0.65 Fares on Hanoi’s first metro will range from VND8,000-15,000 ($0.35-0.65)....
- Vietnam’s first metro line records $2 mln loss in six months Hanoi Metro Company, which operates the Cat Linh-Ha Dong metro line, has reported a loss of VND54 billion ($2.32 million) since putting the line into operation in November last year....
- Hanoi 2nd metro line likely to be delayed by 5 years The Hanoi administration has asked to delay completion of the Nhon-Hanoi Station metro route from this year to 2027 and increase its outlay by VND1.9 trillion ($80.77 million)....
- Hanoi sets new operation deadline for metro line The elevated section of the Nhon-Hanoi Station metro line should start running in August, Hanoi has recently announced after the city missed the previous deadline....
- Vietnam Railways posts profits after 3 years of losses State-owned Vietnam Railways reported profits of VND94.8 billion (US$3.89 million) for 2023 as it returned to the black after three years of losses....